One question I get is why I fit the water stops after the first coat of waterproofing. I like having the area beneath each stop sealed as well. I filmed this bathroom over two days so you can see exactly how I do it, from rounding the edge of the strip drain recess to rolling the final coat.
It’s Jack from Jax Tiling. This is the full bathroom waterproofing tutorial from a job here in Australia. If you came for a particular detail, the times below will take you straight to it.
Preparing the bathroom floor and strip drain
I start at the strip drain. At 0:27 you can see the sharp edges I round off before I bring the membrane into the recess. It’s worth looking at that edge now, because once it’s coated you won’t see what the membrane is sitting on.
At 2:34 I prime the walls and floor. The PVC flange gets its own close-up at 3:33. Watch where the bathroom floor meets the lip of the flange. I show how I prepare and prime that surface before moving on to marking out and masking the room.
Bond breaker, reinforcing band and pipe penetrations
At 10:06 I apply the bond breaker where the wall sheets meet the floor. At 15:47 I bring in the waterproofing membrane and reinforcing band. The corner work starts at 17:01. You can follow the band along the junction and see how I handle the change of direction at an inside corner.
Skip to 21:29 for the pipe penetrations and drains. These close-ups show where the membrane meets the plumbing while everything is still visible. Once those details are done, I roll the first coat over the room at 25:54.
Setting out the shower and doorway water stops
Day two starts at 28:44 with an inspection of the first coat. At 30:09 I set up the green laser to mark where the shower screen glass will sit. That gives me a line to follow on the floor and up the wall.
There are three separate details to watch here. I fit the shower floor water stop at 31:53, the vertical water stop at 38:44 and the doorway water stop at 41:42. If you’ve only seen the short clip of me fitting the angle, go back to the start of day two. You’ll see the coat underneath it and how I chose its position before fitting it.
Checking the floor waste and rolling the final coat
At 47:18 I apply the second coat. I come back to the floor waste at 49:42 for one last look before rolling the final coat at 49:55. If you want to see how the drain detail changes as the job progresses, compare that last close-up with the bare flange at 3:33. It’s the same spot, before and after waterproofing.